Tracking Of Construction Progress Concerning Activity Wise Equipment Delay
B. Indhu1, K. Yogeswari2, Mehnaz Akhtar3

1B.Indhuab, Research scholar, B.S. Abdur Rahman Crescent Institute of Science and Technology, Chennai, India; bAssistant Professor, SRM Institute of Science and Technology, Chennai, India.
2K.Yogeswari, Associate Professor, B.S. Abdur Rahman Crescent Institute of Science and Technology, Chennai, India.
3Mehnaz Akhtar, Department of Civil Engineering, SRM Institute of Science and Technology, Chennai, India. 

Manuscript received on 5 August 2019. | Revised Manuscript received on 11 August 2019. | Manuscript published on 30 September 2019. | PP: 1883-1892 | Volume-8 Issue-3 September 2019 | Retrieval Number: C4459098319/19©BEIESP | DOI: 10.35940/ijrte.C4459.098319
Open Access | Ethics and Policies | Cite | Mendeley | Indexing and Abstracting
© The Authors. Blue Eyes Intelligence Engineering and Sciences Publication (BEIESP). This is an open access article under the CC-BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/)

Abstract: Delay in construction is considered as one of the major drawbacks in the construction world as the delay can increase the cost of the construction project, therefore, it is important to study the causes of it and then analyzing the factors. In this paper, various studies of literature review and a pilot study were done by taking interviews of the experts related to equipment in the construction project. The questionnaire was prepared related to delay in construction due to the equipment delay factor. These questionnaires were divided into the top 5 categories which consist of 20 major causes. The questionnaire survey was sent to the respondents through the google form and personally to the sites. Totally 200 responses were collected for 11 activities. The analysis is done in Relative Important Index (RII) to calculate the highest factors and the lowest factors which cause or effect the delay in construction. Based on the results recommendation were given. The purpose of this project is to deliver the construction facilities rapidly, which do not only serve as a competitive lead but also serves in bringing up constructional innovation.
Keywords: Activity wise, construction progress, equipment delay, Relative Importance Index (RII).