Reliability Index of Wind-Solar Hybrid Power Plants using the Expected Energy Not Supplied Method
Ramadoni Syahputra1, Fahrian Noor2, Faaris Mujaahid3, Agus Jamal4, Sudarisman5
1Ramadoni Syahputra, Department of Electrical Engineering, Universitas Muhammadiyah Yogyakarta, Yogyakarta, Indonesia.
2Fahrian Noor, Department of Electrical Engineering, Universitas Muhammadiyah Yogyakarta, Yogyakarta, Indonesia.
3Faaris Mujaahid, Department of Electrical Engineering, Universitas Muhammadiyah Yogyakarta, Yogyakarta, Indonesia.
4Agus Jamal, Department of Electrical Engineering, Universitas Muhammadiyah Yogyakarta, Yogyakarta, Indonesia.
5Sudarisman, Department of Mechanical Engineering, Universitas Muhammadiyah Yogyakarta, Yogyakarta, Indonesia. 

Manuscript received on November 19, 2019. | Revised Manuscript received on November 29 2019. | Manuscript published on 30 November, 2019. | PP: 9449-9456 | Volume-8 Issue-4, November 2019. | Retrieval Number: D9733118419/2019©BEIESP | DOI: 10.35940/ijrte.D9733.118419

Open Access | Ethics and Policies | Cite  | Mendeley | Indexing and Abstracting
© The Authors. Blue Eyes Intelligence Engineering and Sciences Publication (BEIESP). This is an open access article under the CC-BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/)

Abstract: This paper proposes the reliability index of wind-solar hybrid power plants using the expected energy not supplied method. The location of this research is wind-solar hybrid power plants Pantai Baru, Bantul, Special Region of Yogyakarta, Indonesia. The method to determine the reliability of the power plant is the expected energy not supplied (EENS) method. This analysis used hybrid plant operational data in 2018. The results of the analysis have been done on the Pantai Baru hybrid power plant about reliability for electric power systems with EENS. The results of this study can be concluded that based on the load duration curve, loads have a load more than the operating kW of the system that is 99 kW. In contrast, the total power contained in the Pantai Baru hybrid power plant is 90 kW. This fact makes the system forced to release the load. The reliability index of the power system in the initial conditions, it produces an EENS value in 2018, resulting in a total value of 2,512% or 449 kW. The EENS value still does not meet the standards set by the National Electricity Market (NEM), which is <0.002% per year. Based on this data, it can be said that the reliability of the New Coast hybrid power generation system in 2018 is in the unreliable category. Index Terms:
Keywords: Renewable energy, hybrid system, wind energy.
Scope of the Article: Renewable Energy Technology.